How do I back up assessment data before re-normalizing a supplier name?

Created by Amit Kadam, Modified on Wed, 22 Jul at 10:36 AM by Amit Kadam

  • Before supplier re-normalization, you can export all existing assessment data from the portal. 
  • BCP & Custom Assessments: 
    • Navigate to: Hamburger Menu → Action Center → Assessments → Assessment Responses → Consolidated Responses
    • Export/download the supplier’s responses 
  • SCV Assessments: 
    • Navigate to: Hamburger Menu → Action Center → Assessments → Track Assessment
    • Export/download the SCV data 
  • These exports act as a complete backup of submitted responses and can be used for future reference.