- The Activity field in CDIF is a predefined dropdown, meaning only standard values can be selected (e.g., Assembly, Manufacturing, Logistics, Testing, Warehouse, etc.).
- Please find the attached file for the complete list of supported Activity values.
- Multiple activities per site:
- Yes, a site can have multiple activities. To configure this:
- Add separate rows in the Site List tab (Tab 6)
- Use the same Site Number
- Select a different Activity in each row
- Provide the corresponding Recovery Time
- Note:
- Multiple values in a single cell (e.g., semicolon-separated) are not supported
- The same approach applies to Tab 7 (Part-Site Map) and Tab 8 (Product-Site Map)
- Activity and Recovery Time must always be provided together