- Max Impact Duration refers to the maximum impact duration confirmed by any supplier, either at the Supplier level or Site level, in a WarRoom.
- When multiple suppliers or sites are impacted in a WarRoom and each confirms an impact duration, the highest of these durations is recorded as the Max Impact Duration at both the Supplier and Site levels.
Example:
- In the following example, two suppliers—LUXIM TECHNOLOGY and STAN METALS—have confirmed impact durations of 32 and 42 weeks respectively:
-
- These durations are also reflected on the Sites grid for their respective sites:
-
- Since 42 weeks is the highest confirmed impact duration, it is set as the Max Impact Duration for both the Supplier and Site levels in the WarRoom, as shown in the screenshot below: