Why does impact status remain ‘Potential’ even after Tier 1 sites respond ‘No Impact’?

Created by Rohit Sawant, Modified on Wed, 17 Dec at 12:14 PM by Rohit Sawant

  • This behaviour occurs when a “No Impact” response has been submitted for Tier 1 sites, but the confirmation notifications for Tier 2 sites have not yet been sent or their responses are still pending.
  • In such cases, the system considers the overall event response as partial and continues to display the impact status as “Potential.”
  • The impact status will only be updated once all relevant tiers (e.g., Tier 1, Tier 2) have submitted their responses. Until then, the system retains the “Potential” status to indicate that the data collection is incomplete.